Construction update March 2024 Serene Condominium Phuket
Work for building A

2nd Floor
1. Architecture
- Wall work: 95%
- Floor work: 90%
- Ceiling work: 90%
- Paint work: Floors: 10%
- Corridoor work: 0%
2. Buil-In work
- Furniture: 15%
- Install equipment: 15%
3. System work
- Sanitary ware installation work: 90%
- Installation of electrical equipment: 15%
- Electrical conduit laying work: 100%
- Air conditioning installation work: 90%

3rd Floor
1. Architecture
- Wall work: 95%
- Floor work: 45%
- Ceiling work: 70%
- Paint work: Floors: 10%
- Corridoor work: 0%
2. Buil-In work
- Furniture: 0%
- Install equipment: 0%
3. System work
- Sanitary ware installation work: 80%
- Installation of electrical equipment: 0%
- Electrical conduit laying work: 100%
- Air conditioning installation work: 90%

4th Floor
1. Architecture
- Wall work: 100%
- Floor work: 20%
- Ceiling work: 70%
- Paint work: Floors: 0%
- Corridoor work: 60%
2. Buil-In work
- Furniture: 0%
- Install equipment: 0%
3. System work
- Sanitary ware installation work: 80%
- Installation of electrical equipment: 0%
- Electrical conduit laying work: 80%
- Air conditioning installation work: 90%

5th Floor
1. Architecture
- Wall work: 90%
- Floor work: 0%
- Ceiling work: 0%
- Paint work: Floors: 0%
- Corridoor work: 60%
2. Buil-In work
- Furniture: 0%
- Install equipment: 0%
3. System work
- Sanitary ware installation work: 80%
- Installation of electrical equipment: 0%
- Electrical conduit laying work: 80%
- Air conditioning installation work: 90%

6th Floor
1. Architecture
- Wall work: 10%
- Floor work: 0%
- Ceiling work: 0%
- Paint work: Floors: 0%
- Corridoor work: 0%
2. Buil-In work
- Furniture: 0%
- Install equipment: 0%
3. System work
- Sanitary ware installation work: 75%
- Installation of electrical equipment: 0%
- Electrical conduit laying work: 60%
- Air conditioning installation work: 60%

7th Floor
1. Architecture
- Wall work: 75%
- Floor work: 0%
- Ceiling work: 0%
- Paint work: Floors: 0%
- Corridoor work: 0%
2. Buil-In work
- Furniture: 0%
- Install equipment: 0%
3. System work
- Sanitary ware installation work: 60%
- Installation of electrical equipment: 0%
- Electrical conduit laying work: 50%
- Air conditioning installation work: 60%

8th Floor
1. Architecture
- Wall work: 85%
- Floor work: 0%
- Ceiling work: 0%
- Paint work: Floors: 0%
- Corridoor work: 0%
2. Buil-In work
- Furniture: 0%
- Install equipment: 0%
3. System work
- Sanitary ware installation work: 60%
- Installation of electrical equipment: 0%
- Electrical conduit laying work: 50%
- Air conditioning installation work: 60%

Work for building B
1. Work for 1st floor. = 100%
2. Work for 2nd floor. = 100%
3. Work for 3rd floor. = 100%
4. Work for 4th floor. = 100%
5. Work for 5th floor. = 100%
6. Work for 6th floor. = 100%
7. Water pump room, east side = 100%
8. West swimming pool=100%
9. Western gutter = 100%
10. Stairs work 2nd floor to 3rd floor
Details of construction