Construction update February 2024 Serene Condominium Phuket
Work for building A

Wall work:
Floor 1st = 15%
Floor 2nd = 85%
Floor 3rd = 83%
Floor 4th = 75%
Floor 5th = 50%
Floor 6th = 40%
Floor 7th = 50%
Floor 8th =75%

Floor work:
Floor 2nd = 70%
Floor 3rd = 15%

System work:
Floor 1st = 50%
Floor 2nd = 80%
Floor 3rd = 70%
Floor 4th = 80%
Floor 5th = 70%
Floor 6th = 50%
Floor 7th = 50%
Floor 8th = 50%

Aluminium Fins + Planter + Curb floors:
Floor 2nd = 85%
Floor 3rd = 80%
Floor 4th = 70%
Floor 5th = 10%
Floor 6th = 10%
Floor 7th = 10%
Floor 8th = 10%

Work for building B:
Work for 1 – 6 st floors = 100%
Water pump room, east side = 100%
West swimming pool=100%
Western gutter = 100%
Details of construction